Posted Wednesday 4th March 2020
“We are prepared: we build our houses squat,
Sink walls in rock and roof with good slate.”
Storm on the Island by Seamus Heaney
Any party involved in a construction project is at risk of a claim that is in breach of a duty to warn; although such allegations are most commonly made by a client against a professional consultant.
In the leading the case Goldswain v Beltec Limited [2015] in the Technology and Construction Court, Judge Akenhead summarised 5 principles regarding the duty to warn:
Any claim alleging a duty to warn will necessarily be fact-specific.
Duty to warn cases involving contractors in respect to their knowledge of site conditions have often been decided by confining the contractor’s duty narrowly with respect only to their workmanship obligation.
A supplier may have a duty to warn if it knows, or ought reasonably to know, that a certain material would or may create problems when used in conjunction with its product.
A professional consultant may have a duty to warn in relation to how a building contract or subcontractor carries out the works.
In practice a professional consultant is particularly vulnerable to an allegation that it has breached a duty to warn. This is due to a professional consultant often has an over-arching ongoing role on a project. It may be involved from conception through to completion and during the defects liability period. As a skilled professional with an advisory role, its duty to exercise skill and care may be interpreted widely in law.
The duty to warn aspect of the duty of a professional to act with the skill and care of a reasonably competent person in that profession overlaps with other duties; such as a duty to check the design of other firms engaged in the project or the duty to inspect or supervise the works.
The case law has suggested that the duty of warn may also be extended further in certain circumstances, for instance:
A court held that a project manager should have advised its client of the limited protection afforded by letters of intent: they should have made every effort to execute a formal building contract.
A court held that a project manager had a duty to warn the employer if other members of the professional team were not performing their respective duties (although the court reached this conclusion in that case on the basis of particular terms of the project manager’s appointment).
A court has held that where there are risks inherent with using a new or bespoke or untested design, a professional designer has a duty to warn its client of this and obtain express approval to continue.
What is sufficient warning depends upon certain factors; including the parties contract, the nature of the danger, if applicable, and, circumstances in which the danger is identified.
Any warning must be made expressly clear, especially if a party is warning about a risk that it is contractually obliged to avoid.
The party may only have to warn those that it has a contractual relationship with or perhaps a local authority. The reasoning for alerting a local authority derives that from a local authority has wide powers to safeguard and protect the public. For example, a local authority can take emergency measures to deal with a dangerous building under Section 78 of the Building Act 1984 and could apply for an injunction under Section 36.
A victim of a breach of a duty to warn who is claiming damages must still satisfy the basic legal requirement of causation; in order words its claim may fail if evidence shows that it would not have heeded the warning in any event if it had been provided with one.
As a general rule of thumb, a professional designer may be responsible for permanent construction works; whereas the contractor is responsible for his working methodology and temporary works. However, the situation on many projects is usually more nuanced than that, to the effect that:
This article is for reference purposes only. It does not constitute legal advice and should not be relied upon as such. Specific legal advice about your specific circumstances should always be sought separately before taking or deciding not to take any action.